COUNTY ROUTE # |
ROAD NAME |
LOCATION |
PROJECT |
CR-26 |
Garfield-East Nassau Road |
Town of Stephentown
(2.1 Mile Section beginning at the Junction of Gentile Road Northeast to Break in Pavement past South Road) |
Road is scheduled for chip seal surface treatment during the week of August 2nd, 2010. The road will remain open to traffic, however a 15 m.p.h. speed will be posted for several days to allow the chip seal to compact properly. |
CR-41 |
Dutch Church Road |
Town of Berlin
(1.1 Mile Section beginning at the Junction of Taborton Road) |
Road is scheduled for chip seal surface treatment during the week of August 2nd, 2010. The road will remain open to traffic, however a 15 m.p.h. speed will be posted for several days to allow the chip seal to compact properly. |
CR-37 |
Cold Springs Road |
Town of Berlin, Town of Petersburg |
Road is scheduled for chip seal surface treatment during the week of August 9th, 2010. The road will remain open to traffic, however a 15 m.p.h. speed will be posted for several days to allow the chip seal to compact properly. |
CR-85 |
South Road |
Town of Grafton
(Quackenkill Creek Bridge is located between Johnson Road and Snyder Road) |
The bridge at the Quackenkill Creek is scheduled to be removed and replaced with a large culvert. Road will be closed to all but emergency traffic beginning July 26th, 2010. The road will be completely closed at that location for a period of several days beginning August 2nd, 2010. Please use the signed Detour Routes. |
CR-100 |
Breeze Hollow Road |
Town of Hoosick |
Road is scheduled for chip seal surface treatment during the week of August 9th, 2010. The road will remain open to traffic, however a 15 m.p.h. speed will be posted for several days to allow the chip seal to compact properly. |
CR-117 |
Melrose-Valley Falls Road |
Town of Pittstown/Town of Schaghticoke
(1.75 Mile Section that loops south of Madigan Road (CR119)) |
Road is scheduled for chip seal surface treatment during the week of August 9th, 2010. The road will remain open to traffic, however a 15 m.p.h. speed will be posted for several days to allow the chip seal to compact properly. |